60W solar street light construction installation instructions

The installation of solar street lights is basically the same as the installation process of traditional street lamps, but there are differences, especially the installation of solar panels and batteries. Solar street lamp installation and construction process: selection of lamp position, basic prefabrication, site installation preparation (battery assembly, assembly of battery board and support frame), lamp post assembly (threading, lamp installation, battery panel bracket installation), lifting, battery Installation, controller installation, lamp pole calibration position, acceptance handover.

60W solar street light configuration price list

60W Solar street light configuration

Serial number

Name

Specification

Quantity

Single price (yuan)

1

LED light source (including lamps)

60W

1set

780

2

Battery

200AH

  Piece

1260

3

solar panel

180W

Piece

720

4

Street light pole

8Meter

1Rod

1140

5

Controller

10

 

1set

65

6

Waterproof box + wire


set

200

Product set price (RMB)

4165yuan

Remarks:

1. 12V200AH battery size 522*240*215 (mm) weight: 60KG

2. 180W solar panel size: 1580*808*35mm weight 15KG

3. 60WLED lamp holder: 570*300*82 (mm) weight 10.5KG

4. Street light pole: 8 meters. Upper diameter 70 (mm) Lower diameter 160 (mm) Thick 3.5 Q235 steel plate.

Weight: 105KG

Packing: foam paper packaging

5. Controller: 118*78*32 mm Weight: 0.2KG

6. Waterproof box: 572*280*23(mm) 5KG

7. Wire 12 meters

8. Accessories: several


Description of each component:

1.180W solar panel adopts high efficiency solar cell module with efficiency ≥17%, which has high power generation efficiency;

2.60W high power LED energy saving lamp, efficient and reliable

3.10A intelligent far-infrared remote control photovoltaic charging and discharging controller can realize remote programming and control, and the working mode and working time can be set arbitrarily, and the operation is stable and reliable.

4.12V200AH solar special gel battery, deep cycle design, good recovery, providing 2-3 rainy days normal lighting power;

The inner and outer heat-dip galvanizing treatment of 5.8-meter light pole is strong in corrosion resistance, and it is designed with 10 grades of wind resistance. The shape is simple and generous, and the installation is simple.


Solar Street Light Installation Manual


一.Product schematic (The following pictures are for reference only, please refer to the actual product)




二。Product introduction (The following pictures are for reference only, please refer to the actual product)





















三。Solar lighting site selection requirements

1 The direction of the solar panel should be in the south direction.

2 The array board is selected to be installed around no tall buildings, trees, poles and other unobstructed sunlight and shelter. When it is not possible to meet all-day unobstructed, make sure that there is no obstruction between 9:30 and 15:30.

3 Solar lamps should be kept away from heat sources as much as possible to prevent the life of the lamps from affecting.

4 There should be no direct light source above the solar panel. In order to avoid misidentification caused by misidentification of the luminaire control system.

5 The light pole foundation civil construction should have sufficient strength, and the embedded parts should be reliable and fit with the lamp holder.

6 Protective earthing and lightning protection facilities should be designed in strict accordance with the “Code for Lightning Protection of Buildings” GB557-83. All lamp poles and electrical equipment should have reliable protective grounding and lightning protection facilities. After excavation of the foundation pit, the low pole below 12m shall be immersed in 50mm x 5mm x 1500m galvanized angle steel at the corner of the foundation pit, and the grounding resistance shall be less than 10Ω. When the geological conditions are difficult to achieve, it can be solved by embedding the grounding body and using a resistance reducing agent.


四。Solar LED street lamp foundation structure below 10 meters

6.jpg


(The above picture is for reference only, the actual size can be adjusted according to the height of the pole)


五。

Foundation construction steps

1 Installation of ground-based embedded parts (The following pictures are for reference only, whichever is the actual product)

7.jpg

2 Foundation pit excavation

Survey geological conditions, if the soil is hard, the location of the installation of lamps shall be excavated about 1 cubic meter of pit. If it is soft soil or has special requirements, the excavation depth is determined separately. After confirming the position of the pole, confirm the buried condition of the battery box. Location, preferably 0.5 m from the pole

3 foundation pouring

Place the foundation embedded parts in the foundation pouring pit, and reserve the passage of the battery protection sleeve (hose or PVC pipe). The diameter of the passage is at least 2 times larger than the diameter of the protective casing. The corner of the passage should be as smooth as possible, not at right angles. It is convenient to protect the installation of the casing in the future. Finally, it is poured with C20 concrete, dense and firm.


六。Foundation construction technical requirements

1 Reserve (excavation) 1m3 pit in accordance with the standard at the position of the vertical luminaire, and carry out the positioning and casting of the embedded parts. The embedded part is placed in the middle of the square pit. Pay attention to the pre-embedded parts. The foundation is on the same level as the original ground, and one side should be parallel to the road. This ensures that the rear end of the street light pole is not skewed. Then it is fixed by C20 concrete pouring, and the vibrating rod vibration should not be stopped during the pouring process to ensure the overall compactness and firmness.

2 The allowable deviation of the depth of the foundation pit should be +100mm, -50mm. When the foundation pit depth deviation is more than +100mm due to soil causes, etc., it should be treated as follows:

The deviation is between +100 and +300 and should be treated with stone grouting.

When the deviation exceeds the specified value of +300 or more, the part exceeding 300mm may be filled with soil or sand, and the stone slab shall be treated. The thickness of the layered tamping shall not be greater than 100mm. The density after compaction shall not be lower than that of the undisturbed soil, and then grouting shall be applied. deal with.

3 The length of the anchor bolt embedded in the concrete should be greater than 20 times its diameter, and it should be welded firmly with the main rib. The anchor bolt should be removed from the rust. The threaded part should be protected. The center distribution diameter of the base flange bolt should be the same as the pole base method. The distribution of the center of the blue hole is consistent, the deviation should be less than +1mm, and the bolt should be double nut and spring pad.

4 When pouring the foundation, it should comply with the relevant provisions of the current national standard GB50010-2002. After the construction is completed, the residual sludge on the positioning plate is cleaned in time, and the impurities on the cleaning bolt are cleaned with waste oil. During the concrete solidification process, it is necessary to regularly water the water and maintain it. When the concrete is completely solidified (generally 72h or more), the chandelier can be installed.

5 Foundation pit backfilling should meet the following requirements:

For the soil suitable for compaction, the thickness of each backfill should be tamped once, and the degree of compaction should be 80% or more of the original soil compactness.

For water-saturated cohesive soils that are not suitable for compaction, they should be layered and filled, and the compactness of the backfill should reach 80% or more of the undisturbed soil.


七。Preparation and attention before installation of street lamps

1 The lifting operation must strictly abide by the operating procedures. Special attention should be paid to the power grid lines and other lines around the hoisting equipment, as well as the surrounding structures. The lifting points should be reasonable when hoisting, and should be adjusted in time after positioning.

2 Pay attention to the beauty of the pole after installation. Starting from the foundation construction, the lamp position is controlled linearly according to the main line, and the linear design changes reasonably according to the road design. The lamp post is straight, the processing weld and the inspection port should avoid the main line direction, and the whole line is consistent. The inclination of the pole cantilever is to maintain the coordination of direction and angle.

3 The internal parts of the luminaire should be tightly inserted and inserted firmly to avoid the failure of the wind swaying and poor contact. The lamp and the lamp post, the lamp post and the cantilever are reliably fixed.


八。Solar LED street light installation

Ready to work

1 Disassembly and assembly location selection. The disassembly location should be near the installation location to facilitate post-assembly transportation. Try to avoid working in the rain.

2 Check the luminaire according to the shipping list. Disassemble and refer to the packing list to check each part and check for damage such as bumps, abrasion, deformation and scratches. Lamp pole assemblies and wear-resistant accessories (such as solar modules, lamp holders, etc.) must be placed with a soft mat that is soft to avoid unnecessary damage such as scratches during installation. When the lower pole assembly is placed, an iron frame support is required at the upper end to facilitate the installation of the pole assembly.

3 Check the positive and negative signs of the solar cell module to ensure that the positive and negative terminals are connected correctly. Use a multimeter to verify it to prevent flag errors. Verification method: use the red and black test pens of the digital multimeter to respectively touch the two electrodes of the battery component. If the positive value is positive, the corresponding electrode of the red test pen is positive. If the negative value is negative, the corresponding electrode of the red test pen is negative. The other positive and negative test methods are the same. this.

Installation (The following pictures are for reference only, please refer to the actual product)

1 connection bracket and solar panel


Please handle gently during operation to avoid wear and scratch on the solar glass dry plate.

The fastening screws must be tightened. Take the panel wires out of the direct.

2 connection bracket and light pole


When installing, please calculate the mounting azimuth of the bracket to ensure that the azimuth of the solar panel is positive south after lifting.

After adjusting the angle, tighten the fastening screws to ensure a firm

Take the panel's wires out of the pole to the lower controller position

3 installation lamp head


Install the lamp cover face down, ensuring that the light exits perpendicular to the ground after lifting

After adjusting the angle, tighten the fastening screws to ensure a firm

Take the panel's wires out of the pole to the lower controller position

4 install the battery


Put the battery into the battery box, pad the waterproof gasket, connect the cable and protect the sleeve.

Place the battery in the pit and pull the protective sleeve out of the channel.

5 vertical lights

Before lifting and hoisting, check whether the parts are tight. When the solar panel is facing south (with a compass), the head is facing correctly.

During the lifting process, the installer needs to hold the pole to prevent the components from swaying and rubbing against the ground or the sling.

During the lifting process, the lamp head needs to be adjusted to the road surface. The long hole on the flange is aligned with the anchor bolt. After the flange falls on the foundation, two nuts are placed in turn, and the light pole and the ground are adjusted by the level ruler. Verticality, if not vertical, can be placed under the flange to make it perpendicular to the ground. Finally, tighten the nut evenly with a wrench.



PREV: No more! NEXT: Solar LED street light design

  NEWS

  LATEST NEWS

  CONTACT US

Contact:Mrs.Lei Hu

Phone:+86-15862870707

Tel:+86-514-85083852

FAX:+86-514-85083850

EMIAL:leihu@flohar-lighting.com

CMP:Jiangsu Flohar Lamps Manufacturaing Co., LTD

ADD:Dehua Industrial Park, Guo Ji Town, Gaoyou City, Yangzhou, Jiangsu, China(Mainland)

Scan the qr codeClose
the qr code